PROJECT AUTHORIZATION | PACKET ID: PMT-0OCF |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
9224202C 9224201D | 92242 | 13 | |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
051 004 1 011-015 |
NHPP 3020007 |
02-01088 | 2-.- |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
NEW ROUTE | MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | FHWA | STATE | KYTC | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
2-1088.1 | D | 1100 | FD52 | 2022 | 2022 | $300,000.00 | |
2-1088.1 | D | 1200 | FD52 | 2022 | 2022 | Y001 | $1,200,000.00 |
2-1088.2 | C | 1200 | FD52 | 2022 | 2022 | Y001 | $5,440,000.00 |
2-1088.2 | C | 1100 | FD52 | 2022 | 2022 | $1,360,000.00 | |
CURRENT FUNDING REQUEST TOTAL: $8,300,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $3,220,000.00 |
DESIGN | $20,500,000.00 |
UTILITIES | $1,000,000.00 |
R/W | $26,615,000.00 |
CONSTRUCTION | $192,800,000.00 |
NON-HIGHWAYS | $0.00 |
Total: $244,135,000.00 |
REMARKS: | THIS MODIFICATION PROVIDES $1,500,000 FEDERAL NH FUNDS FOR DESIGN PHASE TO COVER BI-STATE EXPENSES WITH INDOT AND $6,800,000 FEDERAL NH FUNDS FOR CONSTRUCTION PHASE TO COVER IN-LIEU FEES ON THE PROJECT. (STATE FUND MATCH) |
Project Approval Recommended By: James Ballinger 6/9/2022 |
Signed and Approved by: Jim Gray 6/9/2022 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
02-01088.10 | HENDERSON
|
2 | HENDERSON, KY- EVANSVILLE, IN | MI | CONSTRUCT THE PORTION OF THE I-69 ORX PROJECT FROM THE HENDERSON BYPASS (KY 425) TO US 60. (100% KY SHARE) (2020CCR) |